Summer 2008 Work Projects
This list is not yet complete and may be modified:
Dining Hall:
Close in walls of addition - insulate and drywall interior, hang steel siding on exterior
Move shelves and dry goods to new addition when complete
Remove existing walk in cooler
Pour concrete floor for new walk in freezer
Assemble new walk in freezer
Admin Building:
Replace existing doors that exit to the north and south
Build small awnings to protect the new doors
Build a recessed entry for front door
Replace stucco on front of building
Add window to main office
Men's Dormitory:
Replace approx. 20 windows
Replace plumbing in basement bathrooms and laundry areas
New Chapel:
Landscaping
Other jobs to be listed soon
Shop Building:
Enclose walls on vehicle carport
Install (4) roll up steel doors on vehicle building
Install roll up steel door on wood shop
Install roll up steel door on lawn tool shop
Install man door on lawn tool shop
General Campus:
Landscaping and cleanup (always work in this area)